The lead time of mass order for gravity die casting must be more than 40 days




The lead time of mass order for gravity die casting is more than 40 days.

a. Casting process: 80pcs to 120pcs per 12 hours

b. Cutting riser bar and sprue bar, the polishing cutting surface - 5 - 10 days.

c. If there are defect on casting, we need to weld them and polish them again. - 3 - 6 days.

d. Heat treatment 2-4 days

e. Machining 7-15 days


When we got your orders, we are busying on other POs, so we need more than 10 days to arrange your casting. 